Reports - Postponed Schedule Workers

1 - Introduction

The Postponed Schedule Workers report will display all workers that had a postponement for any reason.


2 - Permissions

To access this page, the option “Postpone Logistic Schedule" must be granted to the responsible profiles for controlling the functionality. This enables the button “Postpone” to effectively postpone a crew change. This process creates a new schedule on the next day, taking with it the workers that were selected.

To grant such permission, read the article: Granting Access Permissions.

 


3 - Postponing a schedule

3.1 This postponement can be done by following the path: Tasks> Crew Change> Logistic Schedules.

3.2 The window Logistic Schedule will be displayed listing all existing schedules on the system.Click on the schedule to postpone.

Obs.: This process will not be possible with closed schedules.



3.3 On the selected schedule  page, click on "Postpone".

3.4 A new window will open to select the workers that will have their schedule postponed. This action can be done to one worker or the entire schedule. 

Click on “OK” to confirm.

Obs.: After postponing, a new schedule will be created for the next day.


4 - Access to Postponed Schedule Workers page

4.1 To view the participants of the postponement, go to: Reports > Crew Change > Postponed Schedule Workers

 

4.2 The page below will be displayed. Here is possible to view all the workers that have a postponed schedule.

Caso surja alguma dúvida, entre em contato com nosso suporte através do E-mail: suporte@sapiensia.com / ou Telefone em: +55 (21) 2391-4726